The City Dock project now has a published schedule with dates on it. A buyer who closes after the holidays on Prince George Street, Duke of Gloucester Street or the lower end of Main Street will move in after Barry Gate's expected December reopening and before the boardwalk, the park and the end of Phase Two, all of which fall within roughly the next 18 months. The city says spring and summer of 2026 were the peak of heavy construction. The calendar shows how much of the remaining work the next owner will actually live alongside, and on which streets.
The Schedule the City Published in August
On August 25, 2026, Mayor Jared Littmann led a press conference and site tour. There he announced that the project was on budget and ahead of schedule, and he released a revised timeline. According to the City of Annapolis announcement, the Naval Academy is expected to reopen Barry Gate in December 2026. The Ego Alley boardwalk is due to reopen to pedestrians in March 2027. City Dock Park and the Maritime Welcome Center are scheduled to open in July 2027. A revised Phase Two runs from summer 2027 to spring 2028.
That release also said the spring and summer of 2026 were the peak of heavy construction at the site. The schedule has moved before. The project's July 2026 construction page ran Phase One to May 2027 and put Phase Two between May 2027 and March 2028. The August announcement replaced those dates with the shorter Phase Two window. The project's own site, Access Annapolis, posted a November 5 update saying the work is moving forward. It also notes that approval of the Maritime Welcome Center was affirmed on October 19.
For a buyer, those dates are the useful facts. They put an end date on each kind of disruption and say which blocks each stage affects.
December Reopens the Gate at the Top of Dock Street
During construction, the city rerouted its free Magenta Shuttle to add a stop on Dock Street and Prince George Street, at Barry Gate. The city expects the gate to reopen in December 2026, which it says will bring foot traffic back to the Dock Street business corridor. For homes on the Prince George Street side of the dock, December is the first of the city's dated milestones. We covered how the holiday season is working around the fencing in the meantime in our recent downtown holiday post.
March and July Rebuild the Waterfront Itself
The March 2027 date reopens the boardwalk along Ego Alley. It also lets Watermark return to its berth at Susan Campbell Park and lets boaters use the Ego Alley slips again.
July 2027 is the larger change. The Access Annapolis project description calls for a raised park with lawn, native landscaping, shade and flexible space for public events. On the August site tour, Eye On Annapolis reported that officials pointed out a future water fountain and a stage area with a pergola and an electric building whose steel was already up, with a second electric building planned closer to the city side of the park. The same report noted that Susan Campbell Park itself is not being raised.
The building opening alongside the park is the Maritime Welcome Center. It is planned as the Harbormaster's headquarters and a satellite visitor center, with restrooms, showers and laundry for visiting boaters and direct access to the Harbormaster. The Burtis House is being rehabilitated as part of the same work. A buyer who closes in January would see the park open about six months after moving in.
Phase Two Stays on a Few Named Streets Into 2028
After the park opens, the remaining work is smaller and has addresses. Under the August plan, Phase Two runs from summer 2027 to spring 2028. Instead of one large closure, the work moves through limited sections of Upper Dock Street, the top of Ego Alley and Compromise Street. The city has also said the project's full benefits will not be realized until every phase is finished.
That changes the comparison between nearby houses. A house fronting Compromise Street, or one whose daily route runs down Upper Dock Street, is on the streets where work continues into a second spring. A house a few blocks away on a street the city has not named for Phase Two is not. For a lot of households, that difference matters more than which house is a block closer to the water.
Dock Street Parking Has Moved to the Hillman Garage
Parking near the dock has shifted, and the new arrangement looks set to outlast the fencing. Upper and lower Dock Street had about 120 street parking spaces before construction. By mid-January 2026, The Banner reported that about two dozen remained on upper Dock Street. The city puts the construction loss at about 99 Dock Street spaces. It says the rebuilt Mills Hillman Garage gained 165 spaces to make up for them.
On Dock Street itself, traffic is down to one lane, one way. Parking has been restriped for head-in spaces, with new loading zones and signage, according to the city's August business-support update. On weekends, a free open-air GEM cart runs a loop between the Hillman garage and Dock Street. In October, the Mayor's office listed preparing pay-on-exit at the Hillman garage among its fourth-quarter 2026 goals.
All of this makes a driveway or deeded space near the dock worth even more, a point we covered in our downtown parking post. Guests, contractors and moving trucks now depend on the Hillman garage and Dock Street's head-in spaces.
What the Market Did During the Construction Year
The ZIP code numbers from this fall show buyers kept signing contracts through the construction year. In the 21401 ZIP code, Resideline's market snapshot dated November 9, 2026 shows 38 active listings and 7 pending sales. Resideline calls that pending-to-active ratio of 0.18 a faster-moving market, with listings going under contract faster than in most of the ZIP codes it tracks. As of that November 9 snapshot, current listings had a median asking price of $912,499, and Resideline had been seeing the median active listing for 81 days. Across the 382 closings Resideline tracked in 21401 over the six months before that snapshot, the median sold price was $635,000. Resideline notes that the asking and sold figures describe different sets of homes, so the gap reflects the mix of what is listed versus what sold, not a negotiating discount.
For the whole City of Annapolis, Resideline's report updated November 4, 2026 covers six months of tracked closings. It shows a median sold price of $623,000 and a median of $340 per square foot. Among the 184 closings with both dates on record, the median time from listing to contract was 26 days. Taken together, the two reports describe a split market. Citywide, homes that sold over those six months typically went under contract within about four weeks, while the median 21401 listing still on the market in early November had been visible for close to three times that long. The 21401 figures cover a ZIP code that extends well beyond the historic district, so they describe the conditions a downtown buyer faces rather than a measured City Dock effect.
They also argue against waiting for the fencing to produce a bargain. In a construction year, Resideline still rated 21401 in November as faster-moving than most of the ZIP codes it tracks. For a buyer near the dock, the schedule matters most as a guide to which address to choose. A house on Compromise Street or Upper Dock Street will have Phase Two work outside through spring 2028. A house on a street the city has not named for Phase Two will have the park's July 2027 opening as its last dated milestone.
Questions Buyers Ask About the Blocks Near the Dock
Which streets still have work after the park opens? Under the city's August 2026 plan, Phase Two runs from summer 2027 to spring 2028 in limited sections of Upper Dock Street, the top of Ego Alley and Compromise Street.
Where will guests park on a weekend? The Mills Hillman Garage gained 165 spaces, a three-minute walk from Dock Street by the city's count. A free GEM cart loops between the garage and Dock Street on weekends, and the free Magenta Shuttle stops at Dock Street and Prince George Street.
Does the Phase Two list reach the uphill side of downtown? The streets the city named for Phase Two are Upper Dock Street, the top of Ego Alley and Compromise Street, all at the dock. A buyer weighing both can compare them with our Murray Hill neighborhood guide and our Historic Downtown Annapolis page.
If you are deciding between a house a block from City Dock and one farther up the hill, The Tower Team can walk both with you this winter. We will check each address against the city's Phase Two streets and the Hillman garage, and help you build an offer that reflects which part of the construction calendar you would actually live through.